Installation And Commissioning Of Solvent Recovery Machine

1. Check whether the steam line is blocked or leaking. Pipeline inspection method: turn off the main power switch, loosen the lid lock handle, open the lid, and blow 0.2Bar compressed air from the solvent outlet outside the barrel into the barrel; confirm that the air can be smoothly removed from the barrel The solvent outlet pipe in the barrel blows out.

2. Whether the lid gasket is sealed and leak-free. Inspection method: blow 0.2Bar compressed air into the barrel from the solvent outlet outside the barrel; use soapy water to coat the edge of the barrel lid; if the bubbling is continuous and uniform and the bubbles do not burst, the seal is good, otherwise there will be leakage .

3. Power-on inspection: Check that the fan is operating normally and the heater is heating normally.

4. Preliminarily set the machine according to the boiling point and characteristics of the solvent to be recovered.